Contractor Guide

Make AIA billing match the SOV, the job, and the books

AIA billing is how many contractors bill progress on a job: a period application (commonly G702-style) backed by a continuation sheet of line items (commonly G703-style), tied to a schedule of values, with retainage and prior billings carried forward so the owner, GC, or lender can fund the period. It is progress billing paperwork that has to agree with job costing and the WIP schedule — not a second invoice format you invent each month.

This page is about AIA-style billing literacy for owners and bookkeepers: what G702/G703 mean in plain English, an SOV that matches the estimate, how applications tie to costs and WIP, retainage on the form, why apps get rejected, where QuickBooks Online fits at a high level, and a monthly rhythm with your bookkeeper. The full draw-package stack (waivers, backup, assembly checklist) lives on draw package — link there when you are packing the submission; stay here when you are making the AIA numbers match the books.

Want AIA applications that reconcile to the books every cycle? Call (480) 617-2664, or book the DIG Diagnostic.

The short answer

AIA billing stays useful when seven habits stick:

  1. G702 states the period story; G703 breaks it into lines — current, previous, and to-date billed, retainage, and balance to finish have to foot across both.
  2. The schedule of values is the spine — lines should map to how you estimated and how you cost the job, with approved change orders on the SOV in the same cycle they hit contract value.
  3. Billed-to-date on the application must match the books — job AR / billing history plus retainage held, not a spreadsheet that drifts from QBO.
  4. Percent complete has to mean something the WIP can defend — often cost-to-cost under percentage of completion; "feels like 60%" invites a kickback.
  5. Retainage on the AIA form is money still to collect — track it as a receivable habit on retainage; do not confuse it with lien-waiver paperwork (lien waiver tracking).
  6. QBO holds the books; AIA forms are often prepared alongside — do not invent a built-in "AIA button"; the win is reconciliation, not a feature claim.
  7. Legal and tax leave the books — contract disputes, lien rights, and form sufficiency go to your construction attorney; tax timing and long-term contract elections go to your CPA.

Skip any one and you get familiar friction: an application kicked for math, a WIP that disagrees with billed-to-date, retainage that never hits AR, and a cash plan that slips a cycle.

Blackline Financial is construction-only bookkeeping and advisory for contractors and specialty trades (roughly $1M–$30M). We do not prepare tax returns — tax questions go to your CPA. We do not practice law or decide which AIA edition a contract requires — that is your construction attorney and the contract documents. We keep job costs, billing history, and AIA-ready numbers speaking the same language inside Foundation / Frame; deeper owner packaging often sits in Blueprint. Every engagement starts with a DIG Diagnostic; every package is custom-quoted. Office: 4320 E Brown Rd Suite 103, Mesa, AZ 85205. East Valley and Phoenix-area owners often start from our city pages for Mesa, Gilbert, Chandler, Scottsdale, and Phoenix — this page owns AIA billing literacy and books match; those pages own local hire intent.

What AIA billing is (G702 / G703 in plain English)

"AIA billing" is industry shorthand for progress billing that follows the familiar Application and Certificate for Payment pattern — commonly associated with AIA Document G702 (the application summary) and G703 (the continuation sheet / schedule of values lines). Contracts and lenders use many portals and house forms that look and behave the same way even when the PDF is not an AIA blank. This page uses G702 / G703 as plain-English labels for that pattern — not as a claim that every job must use a specific AIA edition, and not as legal advice about which form your contract requires.

In plain English

PiecePlain-English roleBooks angle
G702-style application Period summary: original contract, approved changes, total completed and stored, retainage, prior payments, current payment due Must reconcile to job billing history, retainage held, and contract value on the WIP
G703-style continuation Line-by-line SOV: scheduled value, prior work, this period, materials stored, total completed, %, balance to finish, retainage Lines should map to estimate / cost codes so % complete is auditable
Schedule of values (SOV) The agreed breakdown of the contract into billable lines Spine of every application; COs update it when approved
Pay application / draw package The full submission stack (application + backup + waivers as required) Assembly checklist on draw package; this page owns the AIA numbers ↔ books story

What owners should get right

  1. Previous + this period = to date — funders reconcile columns; broken math is an instant reject.
  2. Approved change orders only on contract-value and SOV lines — pending COs are not free billing room (change-order accounting).
  3. Retainage % and held-to-date match the contract and the books receivable habit (retainage).
  4. Ask counsel which form / portal the job requires — Blackline's lane is numbers that foot to the books, not form selection or legal sufficiency.

Schedule of values that match the estimate

The SOV is where AIA billing succeeds or fails for the life of the job. A messy SOV creates messy applications every period.

Start from the bid, not from last month's improvisation. Lines should map to how you estimated and how you job-cost — not to whatever was easy to type into the first application. If field cost codes and SOV lines do not talk to each other, every billing cycle becomes a translation exercise.

Approved change orders get lines (or revised lines) in the same cycle. When a CO is approved, update the SOV when you update contract value and estimate-at-completion. Parking approved COs "for later" is how period billings fall behind earned work and show up as underbillings.

Percent complete has to mean something. Pick a method the contract and your WIP can defend — often cost-to-cost under percentage of completion, sometimes units or milestones. Mixing "feels like 60%" on one line with cost-backed % on another is how reviewers kick the package.

SOV habitResult
Lines match estimate + cost codes; COs added when approvedApplication and WIP tell one story
Lump "general conditions" that absorbs everythingReviewers dig; % complete fights every period
Approved COs off the SOVSticky underbillings; cash left on the table
Stored materials without contract language / docsKickback or clawback risk
Prior billed rewritten without a correction trailInstant reject — previous columns are sacred

Previous application columns are sacred. Never "fix" prior billed by rewriting history on a new form without a clear correction trail. Funders reconcile previous + this period = to date.

How AIA billing ties to job costing and the WIP

A funded application your books cannot explain is a future problem — bonding conversations, audit questions, tax timing with your CPA, or the next month-end close. Match before you submit.

Tie these four numbers every AIA cycle

  1. Contract / SOV total (including approved COs only) = current contract on the WIP schedule.
  2. Billed to date on the application = job AR / billing history in the books (plus retainage held, not forgotten).
  3. Costs to date support the % complete story you are claiming — especially under cost-to-cost POC (job costing).
  4. Cash when the application funds hits the right job / invoice — not generic income that orphans the AR.

Over- and under-billing are WIP language for the same mismatch. If you billed ahead of earned revenue, or earned more than you billed, the over-under-billing story and the AIA columns have to agree. AIA billing that ignores the WIP is how owners get surprised at month-end.

Job cost report vs company P&L. Company profit can look fine while jobs bleed — see job cost report vs profit and loss. AIA applications are job-level; they will not fix a company P&L that hides job truth.

Match checkHealthyTrouble
SOV total vs WIP contractSame numberDrift after COs
Billed-to-date vs job AR + retainage heldReconcilesSpreadsheet SOV, orphan AR
% complete vs cost / units methodDefensible"Feels like" %
Funded cash vs open invoicesClears to the jobDump to undeposited / generic income

Retainage on AIA applications

Most AIA-style applications show retainage withheld this period and retainage held to date. That is money you earned (or will earn) but have not collected yet — a receivable habit, not a vague "hold."

Books habit, not form art. When the application shows retainage, the books should show retainage receivable by job (or an equivalent clear tracking method your close can defend). When retainage releases, cash clears the receivable — it is not new revenue. Deep tracking, release timing, and close steps live on retainage.

AIA retainage billing in one sentence. The application states how much was held this period and to date; the books keep that hold visible by job until release; the WIP and cash plan know it is still outstanding.

Do not confuse retainage with lien waivers. Retainage is dollars held. Waivers are payment-chain paperwork. Both show up around progress billing; they answer different questions. Waiver tracking hygiene: lien waiver tracking. Full package assembly: draw package.

TopicThis pageSibling page
Retainage columns on G702/G703Literacy + books match—
Retainage receivable / release / closeLink out/retainage
Waivers in the packageLight mention/lien-waiver-tracking
Full stack + kickbacksLink out/draw-package

Common reasons AIA pay apps get rejected

Reviewers kick applications for substance and for format. Fix the substance in the books first; format is then assembly.

Kickback reasonWhat usually happenedFix habit
Math does not foot Previous + this period ≠ to date; retainage % wrong; balance to finish broken Lock a calc check before submit; never rewrite prior without a trail
SOV ≠ approved contract + COs Pending CO billed; approved CO missing Update SOV same cycle as CO approval (change-order accounting)
% complete indefensible "Feels like" %; costs do not support the claim Align % method with WIP / POC (percentage of completion)
Books disagree with billed-to-date Spreadsheet SOV drifted from QBO / job AR Reconcile application to job billing + retainage held before submit
Stored materials without backup / contract right Materials billed early without docs Only bill stored materials the contract allows, with required backup
Missing backup or waivers Application numbers fine; package incomplete Assemble per draw package; track waivers in AP (lien waiver tracking)
Wrong period / portal / signature rules Format / process miss Follow the contract / funder checklist; counsel for disputes

Cash effect. A kicked application is a timing problem: crews and suppliers still need to be paid, and the period you planned to collect slips. That is why AIA billing belongs in the same conversation as 13-week cash flow when you run one.

Where QuickBooks Online fits (high level)

Searchers ask "does QuickBooks do AIA billing?" and "QuickBooks AIA billing" for a reason: owners want one system. Stay honest at owner level.

What QBO is good at here. Holding customers/projects (jobs), invoices and payments, job costs, and the history you reconcile to each application. Clean QuickBooks Online for contractors hygiene — chart of accounts, items/cost codes, bank feed rules, month-end close — makes AIA reconciliation possible.

What this page does not claim. We do not invent a built-in AIA G702/G703 generator, a specific Intuit product name, or an upcoming feature. Editions and third-party tools change; describe only what your file actually does today, and check Intuit's current docs before anyone claims a button exists. If you prepare AIA PDFs in a portal, spreadsheet, or add-on, the Blackline win is still the same: application columns match QBO job billing, retainage tracking, and WIP.

Practical split

In QBO (typical)Alongside QBO (typical)
Job / customer, invoices, payments, costsG702/G703 PDF or portal upload
Retainage tracking method you can closeFunder-specific cover / signature pages
Reports that feed % complete / WIPLien waivers and backup PDFs

Specialty trades on short tickets still need the same rule when those tickets roll into a GC pay app — see specialty trade bookkeeping.

Monthly rhythm with your bookkeeper

AIA billing is a calendar habit, not a heroic Friday night.

A practical monthly (or draw-cycle) rhythm

  1. Freeze costs and approved COs for the period — job costs posted; approved COs on contract and SOV.
  2. Draft % complete by SOV line from the method you and the WIP defend.
  3. Build or update the G702/G703-style application from that SOV — previous columns locked.
  4. Reconcile billed-to-date and retainage to QBO / job AR before anyone hits submit.
  5. Assemble the package — backup, waivers, portal rules — per draw package.
  6. When funded, clear cash to the right job invoices and update retainage held / released.
  7. Fold exceptions into month-end close — open COs, disputed lines, retainage aging, underbillings.
Rhythm pieceFoundation / Frame seatBlueprint depth
Job costs + billing hygiene Monthly books that can support an application Owner packaging / WIP narrative
AIA ↔ books reconcile Bookkeeper + owner review each cycle Fade, underbilling, and cash plan in fractional CFO conversations
Package assembly Draw backup from the books Lender / surety-ready story when needed (bonding financials)

Every engagement starts with a DIG Diagnostic. Packages are custom-quoted on services — Foundation / Frame / Blueprint only; no public rate card.

What "good" looks like

SignalHealthy AIA billing habit
SOVMaps to estimate / cost codes; COs on the form when approved
G702 / G703 mathPrevious + this period = to date; retainage foots
BooksBilled-to-date and retainage held reconcile to the application
WIPContract, billed, earned, and over/under tell one story
QBOJob history is source of truth; forms prepared alongside without invented feature claims
PackageNumbers here; assembly on draw package
Legal / taxCounsel for forms / disputes; your CPA for tax; Blackline for books hygiene
CloseExceptions listed in month-end close

FAQ

What is AIA billing for contractors?

AIA billing is progress billing using an application-and-continuation pattern commonly associated with G702 (summary) and G703 (line-item schedule of values). It states what was billed before, what is billed this period, retainage held, and the balance to finish — and those numbers must match the job's books and WIP. Many jobs use portals or house forms that behave the same way.

What is the difference between AIA G702 and G703?

In plain English, G702-style forms summarize the period application (contract, changes, completed work, retainage, payment due). G703-style continuation sheets break the schedule of values into lines with prior work, this period, stored materials, percent complete, and balance to finish. Which exact document or portal your contract requires is a contract / counsel question — not something this page decides.

Does QuickBooks do AIA billing?

QuickBooks Online holds the job costs, invoices, payments, and history you reconcile to an AIA-style application. Many contractors prepare G702/G703 PDFs or portal uploads alongside QBO rather than from a single invented "AIA button." Do not assume a built-in generator; check what your edition and any add-ons actually support today. Blackline's focus is reconciliation: application columns match the books. See QuickBooks Online for contractors.

What is AIA retainage billing?

It is how retainage withheld this period and held to date appears on the application, paired with a books habit that keeps retainage receivable visible by job until release. Deep retainage accounting lives on retainage.

How does AIA billing relate to a construction draw package?

The AIA-style application and SOV are the billing spine; the draw package is the full submission stack (application, backup, waivers, and whatever else the funder requires). This page owns AIA numbers ↔ books; draw package owns assembly and kickback checklists.

Why do AIA pay applications get rejected?

Common causes: math that does not foot, SOV out of sync with approved contract and COs, indefensible percent complete, books that disagree with billed-to-date, stored materials without rights or backup, and missing package pieces (waivers, docs, portal rules). Fix substance in the books first, then assemble.

Can Blackline help with AIA billing tied to our books?

Yes — for construction and specialty trades in the roughly $1M–$30M range. Start with a DIG Diagnostic; ongoing books and billing hygiene in Foundation / Frame; owner-level WIP and packaging in Blueprint. Custom-quoted on services / contact. Call (480) 617-2664. We do not prepare tax returns; we do not practice law; we coordinate with your CPA and you keep your construction attorney for contract and form questions.

Ready for AIA billing that matches the books?

Tell us about your construction business and we will put together a custom quote — usually within one business day. DIG first; Foundation / Frame for the monthly seat; no invented rate card.

Book the DIG Diagnostic →

Get a custom quote →

See services and packages →

Call (480) 617-2664

Blackline Financial · 4320 E Brown Rd Suite 103, Mesa, AZ 85205